Saturday 20 February 2010

EDF

Before progressing with any building we wanted toe nsure connecting the house to the electrcity network was going to possible within our budget. The house will be approx. 55 metres from the roadside where our current electrcity meter is situated.

We submitted a request to EDRF whom gave the request to a subcontractor to do a feasibility study. After 2 months (we did have a 2 week Christmas shutdown in the time!) we eventually received the devis (estimate) for the works which was within our budget. So now we are at the beginning of January and ready to get going!